Nissan
project type
Fit-Out
size
4 no. garages of 1500m2 each
location
Dublin,Ireland
timescale
- 4 weeks per garage
- 16 week overall programme
the client
Nissan has been at the forefront of the Irish motor industry since their arrival into Ireland in 1977, a feat that is achieved by a potent combination of aggressive sales and marketing strategies coupled with an extremely strong customer service philosophy.
the brief
The works centered on the strip out and replacement of key features and finishes in the existing garages to raise their already impressive profiles. This was achieved by the introduction of a new bespoke A/V installation, a feature lighting overhaul, addition of glazed meeting rooms for customer interaction, a total hard-flooring uplift and replacement, new joinery, soft furnishings and a full redecoration to create a completely new look-and-feel.
The biggest challenge was to carry out these works, against 4-separate and standalone aggressive installation programmes, whilst the garages remained open for business during the refurbishment process.
It is a testament to the on-site management from the Operations Team that the projects were not only all completed on-time, but the positive impact achieved through the high-quality of the finished works exceeded Nissan’s initial expectations for these flag-ship finished garages.